A Control Level Schedule (Level 3 Schedule or Network Schedule) is an actual project schedule control and management tool for a work level. The Project Control Level Schedule is integrated detailed EPC activities for the entire project scope of work based on a Critical Path Method (CPM) used a network scheduling technology with detailed input all major milestones, major elements of design engineering, procurement, construction, pre-commissioning, and commissioning activities. The Project Control Level Schedule shows detail and individual work tasks and clearly defined works by discipline or responsibility. This is a first level of detailed schedule that a meaningful critical path management can be performed to monitor and manage the overall project work accurately, and usually basis of a look ahead or window schedules for the project schedule control and management.