Relationship (Schedule Logic)

A Relationship (Schedule Logic) is a schedule dependency between activities that can be assigned as four (4) types: Finish to Start (FS), Start to Start (SS), Finish to Finish (FF) and Start to Finish (SF) with a lead or lag duration. (Refer to the Dependency)

Related Definitions in the Project: The Project Schedule