Critical Path

A Critical Path is a sequence of activities in a work package or planning package in the network schedule that has the longest total duration with the least amount of total float or slack through to the end point. The Critical Path leads to the overall project duration calculated by the schedule software application.

Related Definitions in the Project: The Project Management; Project Schedule

Posted in Controls, Management and tagged , , , , .

ThePD (The Project Definition)

ThePD has been developing the Preferred Project Definitions based on the actual project execution and operation experiences and knowledge with the Project Language, and sharing with you daily basis.