Detailed Network Schedule (Level 4 Schedule)

A Detailed Network Schedule (Level 4 Schedule or Execution Schedule or Construction Detailed Schedule) is a detailed and discipline-wide working level network schedule that is the critical path method (CPM) management schedule displaying all detailed activities to be accomplished by the project workforce. The Detailed Network Schedule can be expanded of the Project Control Level (Level 3) Schedule. Sometime, the Detailed Network Schedule is developed by a construction subcontractor based on the Project Control Level (Level 3) Schedule.

Related Definitions in the Project: The Project Schedule; Construction