Level of Schedules are a Project Master Schedule (Level 1), Project Summary Schedule (Level 2), Control Level Schedule (Level 3), Detailed Network Schedule (Level 4), and Reports Schedule (Level 5). The Master or Project Summary Schedule is one of the contract documents, and the Control Level Schedule is a project baseline document.